Leyland Town Centre Deal, Leyland

Client: Eric Wright Construction Ltd
Leyland Town Centre Deal, Leyland
Development is part of a wider regeneration program aimed at transforming the heart of Leyland comprising of 2 new build £38m
Repeat contract from long term client Eric Wright Construction Ltd
contract value on a labour, plant, material basis £2.0m
North Star were able to provide on the back of being awarded this project providing job opportunities for local young people 2 apprenticeships
Site clearance and enabling works package creating suitable and robust access routes for the duration of the construction programme Pile mat formation for vibro piling works Reinforced concrete strip and pad foundations Steel fixing in foundations, lift pits and retaining walls Construction 2 x lift pits Concreting works including waterproof concrete to retaining walls and lift pits

What Works We Completed

One Team, Full Delivery

Enabling works package to clear site and create safe and robust site access routes etc. were completed in accordance with the main project start date. The programme for this element of the contract was very tight but critical for all parties to ensure the main works commenced on time

Foundation works, including placing of bolt boxes, completed in line with steel frame erection dates ensuring no delays to the contract

Two large retaining walls constructed including formwork, steel fixing and concreting works. These retaining walls formed part of the structural design for both buildings and had to be completed prior to the commencement of the steel frames being erected.

Gas membrane and waterproofing systems installed below ground floor slabs along with all interface details with retaining walls and lift pits etc.

350.00m3 attenuation tank supplied and installed as part of the overall drainage strategy

Timely Enabling Works Completion On Schedule Foundation Works Completion Structural Retaining Wall Construction Gas Membranes and Waterproofing Attenuation Tank Installation

Challenges We Worked Through

01

Delivering to a tight programme

The initial enabling works package needed to be delivered and achieved against a tight programme period to ensure the main project works commenced on time. With a combined effort from both the site and management team here at North Star we completed all works to a high standard and in line with the client’s programme requirements

02

Engineering the retaining walls

Two large retaining walls had to be constructed as part of the foundation design for both commercial units which added technical, logistical and sequencing factors to the construction process. Through meticulous planning and regular co-ordination, technical and progress meetings we made sure that the works were delivered in line with all design and specification requirements and within the agreed timescales

03

Coordinating complex waterproofing

A gas and waterproof membrane system was installed to both buildings including various complex interface design details with the retaining walls, lift pits and foundations. North Star engaged the services of a specialist subcontractor and through regular technical and co-ordination meetings we ensured all the necessary preparation works were carried out and that the membrane installations were executed on programme and in line with the design requirements. Independent validation and inspection reports were carried out at various intervals to sign off the works.