What Works We Completed
One Team, Full Delivery
Enabling works package to clear site and create safe and robust site access routes etc. were completed in accordance with the main project start date. The programme for this element of the contract was very tight but critical for all parties to ensure the main works commenced on time
Foundation works, including placing of bolt boxes, completed in line with steel frame erection dates ensuring no delays to the contract
Two large retaining walls constructed including formwork, steel fixing and concreting works. These retaining walls formed part of the structural design for both buildings and had to be completed prior to the commencement of the steel frames being erected.
Gas membrane and waterproofing systems installed below ground floor slabs along with all interface details with retaining walls and lift pits etc.
350.00m3 attenuation tank supplied and installed as part of the overall drainage strategy