Luneside Student Accommodation Scheme, Lancaster

Client: Eric Wright Construction Ltd
Luneside Student Accommodation Scheme, Lancaster
Project comprised of 4 x new build student accommodation blocks located on the banks of the river Lune in Lancaster
Our contracted works were delivered over a period of 12 Month
Contract Value £1.5m
North Star employed following being awarded this contract Local Labour
Pile mat formation for steel encased driven piles Pile cropping Reinforced ground beams and pile caps Steel fixing in foundations, lift pits and GF slabs Construction of 4 x lift pits Concreting works to ground beams, pile caps, lift pits and GF slabs

What Works We Completed

One Team, Full Delivery

Over 300 steel encased reinforced concrete piles were installed on this project which all had to be cut and burnt off at agreed pile cut off levels

This project involved an intensive programme of works to get the foundations constructed and cast as each block was being worked on simultaneously. All blocks were completed in line with the client's programme requirements and in readiness for the steel frame erection dates

All 4 ground floor slabs were poured and finished to desired tolerances and completed on programme to ensure no delays were caused to follow on trades

As the 4 new student accommodation blocks were constructed simultaneously it resulted in regular co-ordination and planning meetings with the client. As a result of this all key milestone dates were met

Large external works package comprising of paviours, street furniture installations, planters and retaining walls, tarmacadam footpaths, roads and car parks and section 278 works. All works handed over to the complete satisfaction of our client. Section 278 works had to be carried out under a partial road closure and associated traffic management requirements

Reinforced Concrete Pile Cutting Coordinated Foundation Works Delivery On Time Ground Floor Slabs Coordinated Delivery, Milestones Met External Works and Infrastructure

Challenges We Worked Through

01

Overcoming COVID Construction Challenges

The biggest challenge we faced as a business on this project was Covid striking during the construction programme. Despite the lockdown restrictions imposed on other industries and business sectors and the potential health implications the government decided that construction was to continue. This created numerous H&S and logistical issues that we had to overcome to ensure the construction process continued and the project progressed. Covid also resulted in a shortage of construction materials as businesses were forced to close meaning that production levels were severely restricted. Despite all this we managed to maintain a presence on site and deliver the works as efficiently as possible

02

Managing Railway Proximity Constraints

There was an existing railway line and viaduct that ran alongside this proposed site which meant certain works were restricted within a certain distance of the structure and exclusion zones were implemented

1/2