Luneside Student Accommodation Scheme, Lancaster
What Works We Completed
One Team, Full Delivery
Over 300 steel encased reinforced concrete piles were installed on this project which all had to be cut and burnt off at agreed pile cut off levels
This project involved an intensive programme of works to get the foundations constructed and cast as each block was being worked on simultaneously. All blocks were completed in line with the client's programme requirements and in readiness for the steel frame erection dates
All 4 ground floor slabs were poured and finished to desired tolerances and completed on programme to ensure no delays were caused to follow on trades
As the 4 new student accommodation blocks were constructed simultaneously it resulted in regular co-ordination and planning meetings with the client. As a result of this all key milestone dates were met
Large external works package comprising of paviours, street furniture installations, planters and retaining walls, tarmacadam footpaths, roads and car parks and section 278 works. All works handed over to the complete satisfaction of our client. Section 278 works had to be carried out under a partial road closure and associated traffic management requirements
