Padiham Grid Substation GT1 Replacement

Client: SP ENW
Padiham Grid Substation GT1 Replacement
Reinforced concrete equipment foundations constructed 40+
New transformer bund & auxiliary bund constructed New Bunds
Existing plinths, transformer bund walls & plinths demolished & removed Demolished
Live operational 132kV Grid Substation maintained throughout works 132kV Grid Substation
Working Within a Live 132kV Grid Substation Existing Underground Services Maintaining Operational Access Groundwater Management Programme Coordination

Maintaining the highest safety standards while working around live electrical infrastructure was critical. Close coordination with SP ENW and completing works under safety standby ensured safe systems of work, controlled access and continuous operation of the site throughout construction.

Challenges we worked through

Working Within a Live 132kV Grid Substation

Maintaining the highest safety standards while working around live electrical infrastructure was critical. Close coordination with SP ENW and completing works under safety standby ensured safe systems of work, controlled access and continuous operation of the site throughout construction.

Existing Underground Services

The project involved extensive excavation in areas containing numerous live underground cables and services. Comprehensive CAT scanning, careful excavation techniques and constant liaison with the client's engineering team allowed works to progress safely without service disruption. Due to positions of existing services when uncovered, liaison with design engineers was critical to allow safe construction while maintaining and protecting cables.

Maintaining Operational Access

SP ENW always required unrestricted access for maintenance teams during construction. Careful planning of temporary fencing, vehicle routes and phased construction ensured operational access remained available throughout the project.

Groundwater Management

Large excavations for transformer bunds presented challenges due to perched groundwater. Temporary pumping systems and phased excavation works enabled construction to continue while maintaining safe and dry working conditions.

Programme Coordination

The project required close coordination between civil works, structural steel installation and SP ENW electrical installation teams. Detailed planning and regular communication ensured each stage was completed in sequence, keeping the overall programme on track.

One Team, Full Delivery

Working closely with SP ENW, our team established the construction compound, working area & temporary works while ensuring safe access was maintained for operational staff within the live Grid Substation. We worked with SP ENW to adjust our programme & utilise resources efficiently to ensure timely completion in line with clients programme.

Site Establishment & Planning

Existing transformer plinths, redundant cable trenches & obsolete reinforced concrete structures were carefully demolished & removed. All works were completed under strict safety controls due to the live electrical environment.

Demolition & Enabling Works

Following excavation works, our team constructed the new reinforced concrete transformer bund, auxiliary bund & over forty equipment foundations. Every element was delivered to engineering tolerances to support future steelwork & electrical infrastructure.

Civil Engineering Construction

Specialist cable troughs, HV duct routes, drainage systems & earthing excavations were completed, allowing SP ENW to undertake the installation of new electrical equipment with minimal disruption.

Cable Infrastructure & Drainage

The final phase included construction of new access roads, drainage channels, lighting installations, reinstatement works & final landscaping before handing the completed project back to the client.

Access & Finishing Works
Site Establishment & Planning Demolition & Enabling Works Civil Engineering Construction Cable Infrastructure & Drainage Access & Finishing Works
Phase 01

Site Establishment , Demolition & Excavation

Construction compound, welfare facilities and temporary fencing were installed. Utility surveys, CAT scanning and enabling works commenced ahead of the main construction programme. Existing transformer plinths, cable trenches and redundant infrastructure were demolished before large-scale excavations began for the new transformer bund and equipment foundations.

Phase 02

Foundation construction (Steel  work and Concreting)

Reinforced concrete transformer bunds, equipment foundations and auxiliary structures were constructed, providing the platform for the new electrical infrastructure.